MSC Positano III

Ngqura Container Terminal, Ngqura (Coega). Visit NCT12582 (MSCINGO).

Not yet in ETA —Planned berthing Wed 2 Dec, 20:00Still to unload —Free storage ends —

Timeline

  • MSC Positano III: planned berthing moved later by 1 d 12 hThu 19 Nov, 15:16 · Now Wed 02 Dec 20:00, was Tue 01 Dec 08:00.
  • MSC Positano III: export stack close moved later by 2 dThu 19 Nov, 13:34 · Now Wed 02 Dec 07:00, was Mon 30 Nov 07:00.
  • MSC Positano III: planned berthing moved later by 3 dWed 18 Nov, 15:29 · Now Tue 01 Dec 08:00, was Sat 28 Nov 08:00.
  • MSC Positano III: export stack close moved later by 3 dTue 17 Nov, 13:56 · Now Mon 30 Nov 07:00, was Fri 27 Nov 07:00.

What the files said, over time

  • Planned berthingSat 28 Nov, 08:00
  • Planned berthingTue 1 Dec, 08:00
  • Planned berthingWed 2 Dec, 20:00

Collection and free time

The terminal has not published free-storage dates for this ship yet.

Exports

  • StackSun 29 Nov, 07:00 to Wed 2 Dec, 07:00Provisional
  • ReefersSun 29 Nov, 07:00 to Wed 2 Dec, 07:00

When boxes can really be collected

First plannedSat 28 Nov08:00
Dues: can collectSat 5 DecCould be as late as Tue 8 Dec
  • Work startsabout Thu 3 Dec, 17:18as late as Fri 4 Dec, 23:29
  • Unloading doneabout Fri 4 Dec, 21:27

Planned for Wed 2 Dec, 20:00. Plans made this far ahead at this terminal have lately slipped by 21 hours (9 ships)